A  few words about CASA Centre Redevelopment Project Progress from CASA CEO Denise Milne

 

 

Good afternoon everyone – I wanted to give you an update on CASA Centre:
  •  An open house for the Allendale community is scheduled for December 4th from 6:00 pm  to 8:00 pm at the Allendale Community Hall; a meeting with the Allendale Community League occurred two weeks ago.  The Allendale community is very supportive of CASA and is keen on being involved in the building process and we will continue to have ongoing meetings with the community;
  • The Hazardous materials are being dealt with and completion by mid-December;
  • Clark Builder is the successful Construction Management firm for phase 1;
  • The demolition of the old building is slated for January with an anticipation construction start in early spring;
  • We will continue our user group meetings with staff and a family member from the CASA Family Advisory Council along with IBI and Clark Builders, and;
  • We will also have bi-weekly meetings with Clark and IBI as we journey through this process.